On the pricing chart below; the “Basic“, “Mid” & “Upper” levels distinguish which the types of features and finishes you need.  Most projects fall between the Mid and Upper Levels.  Design, labor, materials, flooring, countertops and fixtures are included in the following estimates. Items NOT included are listed at the bottom.

BASIC LEVEL KITCHENS

Small
$26-$32k
100-120 sqft
5-6 weeks
Medium
$30-$35K
120-144 sqft
6-7 weeks
Large
$35-$40k
144-180 sqft
7-8 weeks
  • Use existing cabinet layout
  • Modular pre-finished cabinets
  • Black or white appliances
  • Free standing range
  • Dishwasher
  • Disposal
  • Hood vent
  • Laminate Countertops w/4” splash
  • Double bowl sink
  • Sheet vinyl flooring
  • New cabinet crown molding and baseboards
  • Paint walls & ceiling 2 colors
  • Plumbing to remain in existing locations

MID LEVEL KITCHENS

Small
$29-$34k
100-120 sqft
5-6 weeks
Medium
$34-$39K
120-144 sqft
6-8 weeks
Large
$39-$44k
144-180 sqft
8-10 weeks
  • Minor changes to cabinet layout
  • Modular pre-finished cabinets
  • Raised panel doors
  • Stainless appliances
  • Free standing or slide in range
  • Dishwasher
  • Disposal
  • Microwave hood
  • Quartz or Granite countertops
  • Undermount sink
  • Deck mount Faucet w/sprayer
  • Ceramic tile flooring
  • New cabinet crown molding and baseboards
  • Paint walls & ceiling 2 colors

UPPER LEVEL KITCHENS

Small
$48-$53k
100-120 sqft
9-10 weeks
Medium
$53-$58K
120-144 sqft
10-11 weeks
Large
$58-$63k
144-180 sqft
11-13 weeks
  • Changes to cabinet layout
  • Drywall repairs as needed
  • Recessed lighting
  • Custom built cabinets
  • Raised panel doors
  • Stainless appliances
  • Cooktop
  • Double Oven
  • Dishwasher
  • Microwave hood
  • Quartz or Exotic Granite countertops
  • Undermount sink
  • Deck mount Faucet w/sprayer
  • Disposal
  • Vinyl plank, porcelain or ceramic tile flooring
  • New cabinet crown molding and baseboards
  • Paint walls & ceiling 2 colors

 

NOT INCLUDED

  • Smoke Detectors-Carbon Monoxide Alarms
  • Permit fees
  • Drafting
  • Dry rot/termite/mold damage
  • Asbestos abatement
  • Electrical panel upgrades
  • Code upgrades
  • Refrigerators